The measured mile is the most accepted way to quantify lost productivity there is. It needs one thing: a period of clean work to compare against, identified at the time. Almost nobody records that — so by the time the claim matters, the evidence for it never existed.
The measured mile — comparing productivity in disrupted periods against your own clean periods — is the most widely accepted technique there is, and AACE 25R-03 names it a preferred methodology.
Everyone agrees on how to do itLost productivity is usually not tracked separately at the time. Two years later nobody can say which weeks were clean, which were disrupted, or why.
No clean period means no measured mileRebuilt from timesheets and memory long after the fact, the baseline becomes an argument rather than a record — and the other side gets to pick it apart.
Contemporaneous or not at allA claim that quietly includes your own inefficiency invites a line-by-line attack that takes the credible part down with it.
Honesty is a tactic, not just ethicsLate drawings in Area B, stacked trades in Area C, blocked access, one rework event that was our own fault, and exceptional weather. The register classifies every period automatically from the events log.
Quantity and man-hours by period, area and trade. Weekly, minutes to keep. Everything else derives from it.
What disrupted the work, where, when, and whose fault — with AACE-style cause codes and a Client / Contractor / Neutral tag.
Finds your clean periods per trade and builds a quantity-weighted baseline rate, then computes lost hours against it.
Lost hrs = actual − (qty ÷ baseline rate)
Flags thin baselines and crew mismatches — the two things that get a measured mile thrown out.
Lost hours priced with on-costs, counting only what someone else caused, plus a pre-submission check.
If you run the Progress Measurement System, the quantities and earned hours it produces feed straight in.
Kept weekly it costs minutes. Reconstructed later it usually cannot be done at all.