Every planner receives schedules they do not trust — open ends, negative lag, hard constraints, activities dragged into place rather than linked. The DCMA 14-point assessment catches all of it, mechanically. Paste your export in, read the scorecard.
The workbook ships loaded with a 40-activity sample that deliberately fails. This is the scorecard it produces the moment you open it.
A schedule that looks perfectly reasonable as a Gantt chart, and is structurally unusable.
DCMA thresholds by default, and every one of them adjustable on the Settings sheet if your client works to different tolerances.
| # | Check | Threshold | Why it matters |
|---|---|---|---|
| 1 | Logic | <5% open ends | Activities missing a predecessor or successor. The schedule cannot calculate properly without complete logic. |
| 2 | Leads (negative lag) | zero | Negative lag hides logic and corrupts the critical path. There is never a good reason for it. |
| 3 | Lags | <5% | A lag is usually a missing activity in disguise. Model the work instead of padding the link. |
| 4 | Relationship types | >90% FS | Finish-to-Start should dominate. Heavy SS/FF use is usually overlapping guesswork. |
| 5 | Hard constraints | <5% | Constraints override logic. The schedule stops being a network and becomes a wish. |
| 6 | High float | <5% over 44d | Excess float almost always means missing successors, not genuine slack. |
| 7 | Negative float | zero | Negative float means the schedule is already impossible as drawn. |
| 8 | High duration | <5% over 44d | Long activities hide progress. If it runs over two months, break it down. |
| 9 | Invalid dates | zero | Actuals in the future or forecasts in the past mean the update was not done properly. |
| 10 | Resources | <5% | Activities with duration but no cost or resource cannot be earned against. |
| 11 | Missed tasks | <5% | Activities finishing later than baseline. The rate of slippage matters more than the count. |
| 12 | Critical path test | manual | Add 600 days to a critical activity and confirm the finish date moves by the same amount. |
| 13 | CPLI | ≥0.95 | Critical Path Length Index. Below 0.95, the finish date is not realistically achievable. |
| 14 | BEI | ≥0.95 | Baseline Execution Index. Tasks actually finished against those that should have been. |
Fourteen checks. Ten seconds. One paste.