NEC4 Programme Compliance Tracker

A quarter of your money, held for a missing document

Under NEC4 clause 50.5, while there is no submitted programme the Project Manager withholds one quarter of the Price for Work Done to Date from every certificate. On £8.4m of work done that is £2.1m of your cash in someone else's account — and it is not a penalty for a bad programme. It is a retention for a missing one.

See the 31.2 checklist

What the sample project shows

NEC4 ECC Option C, four programme revisions, none accepted

£8.4m Price for Work Done to Date. Rev 0 and Rev 1 rejected for missing clause 31.2 content. Rev 2 rejected because the PM disliked the piling sequence. Rev 3 submitted 6 July — no response.

Withheld
£2.1M
Days held
105
Financing cost
£54k
31.2 items missing
4 of 11
Two findings the register produces on its own. Rev 2 was rejected on a ground that does not exist — disagreeing with a practicable, compliant method is not one of the four permitted reasons. And the PM is 42 days past the two-week response period on Rev 3. Both are now documented, dated and arguable. Neither was visible in an email thread.

The eleven things clause 31.2 requires

Miss any one and the programme can be rejected on ground 2 — and the retention stays where it is. Score it before you submit, not after.

#The programme must show
1Starting date, access dates, Key Dates and Completion Date
2Planned Completion
3Order and timing of the operations the Contractor plans to do
4Order and timing of the work of the Client and Others
5Float
6Time risk allowances
7Health and safety requirements
8Dates when the Contractor needs access to parts of the Site
9Dates the Client provides materials, facilities and Plant
10Dates for acceptances and information from Others
11Statement of method, with principal Equipment and resources

Time risk allowances, Others' work and health and safety requirements are the three most commonly missed.

Only four grounds are valid

NEC4 permits exactly four reasons for not accepting a programme. Anything else is not a rejection you have to accept quietly.

Ground relied onStatusWhat it means for you
1. Not practicable Valid The PM must explain why the method cannot be built as drawn.
2. Missing information Valid The one you control — and the one the 25% retention turns on. Close it and it disappears.
3. Not realistic Valid But the PM must say what is unrealistic. "Too optimistic" with no analysis is not a reason.
4. Does not comply with the Scope Valid Ask which Scope clause the programme conflicts with.
Disagreeing with your method NOT valid If the sequence is practicable, realistic and compliant, preference is not a ground.
Fear of conceding a compensation event NOT valid Acceptance does not concede entitlement, and worrying that it might is not a ground.

Building Safety Act gateways

Gateway approvals are acceptances from Others, so clause 31.2 requires them on the programme. They are also enormous, and most programmes understate them badly.

Gateway 2 runs at a 43-week median

48 weeks in London. No construction on a higher-risk building may start until it is approved, and over 1,500 applications have been sitting in progress.

A 12-week allowance understates it by 40 weeks

Roughly a quarter are not approved first time

The approval rate has run at about 77%. The tool computes a probability-weighted duration including the resubmission branch, rather than assuming first-time success.

Expected duration, not best case

Gateway 3 blocks handover

Completion certificate before occupation. Cases have waited more than 500 days — that is revenue deferred, not just a milestone missed.

Occupation, and income, wait on it

Pricing

NEC4 Compliance Tracker

$249
One-time purchase
  • Clause 31.2 pre-submission checklist
  • Submission register & two-week clock
  • Retention exposure calculator
  • Invalid-rejection analysis
  • Building Safety Act gateway model

Schedule Quality

$149
The natural pair
  • All 14 DCMA checks
  • Is the schedule built properly?
  • Different question to 31.2
  • Most planners need both
See the Analyser

Questions

Yes. NEC4 clause 50.5: where the Contractor has not submitted a first programme for acceptance, the Project Manager withholds one quarter of the Price for Work Done to Date from payment. It is released once a programme is submitted showing what clause 31.2 requires — it does not depend on the PM agreeing with the plan.
Exactly, and that is the useful part. If the programme was issued and shows the required information, the retention should not be taken even if the PM thinks the plan is wrong. That makes it a checklist problem, which is a solvable problem.
Different question entirely. The Analyser asks "is this schedule built properly?" using the DCMA 14-point checks. This asks "does this programme contain what the contract demands?" A programme can pass DCMA and still be rejected under 31.2, and vice versa. Most planners need both.
It cannot judge whether your plans are practicable or realistic — grounds 1 and 3 — which stay matters of engineering judgement. It closes ground 2, which is what most rejections actually rely on and the only one the retention turns on. It is not legal advice.
Because gateway approvals are acceptances from Others, and clause 31.2 requires those on the programme. Gateway 2 has been running at a 43-week median with roughly a quarter not approved first time. A programme showing 12 weeks for it is not a programme, it is a hope.
Largely. The clause numbering differs and NEC3 has no direct equivalent of the 50.5 retention, but the 31.2 content requirements are close enough that the checklist still applies.

Stop financing someone else's paperwork

Eleven items. One checklist. A quarter of your money.