Under NEC4 clause 50.5, while there is no submitted programme the Project Manager withholds one quarter of the Price for Work Done to Date from every certificate. On £8.4m of work done that is £2.1m of your cash in someone else's account — and it is not a penalty for a bad programme. It is a retention for a missing one.
£8.4m Price for Work Done to Date. Rev 0 and Rev 1 rejected for missing clause 31.2 content. Rev 2 rejected because the PM disliked the piling sequence. Rev 3 submitted 6 July — no response.
Miss any one and the programme can be rejected on ground 2 — and the retention stays where it is. Score it before you submit, not after.
| # | The programme must show |
|---|---|
| 1 | Starting date, access dates, Key Dates and Completion Date |
| 2 | Planned Completion |
| 3 | Order and timing of the operations the Contractor plans to do |
| 4 | Order and timing of the work of the Client and Others |
| 5 | Float |
| 6 | Time risk allowances |
| 7 | Health and safety requirements |
| 8 | Dates when the Contractor needs access to parts of the Site |
| 9 | Dates the Client provides materials, facilities and Plant |
| 10 | Dates for acceptances and information from Others |
| 11 | Statement of method, with principal Equipment and resources |
Time risk allowances, Others' work and health and safety requirements are the three most commonly missed.
NEC4 permits exactly four reasons for not accepting a programme. Anything else is not a rejection you have to accept quietly.
| Ground relied on | Status | What it means for you |
|---|---|---|
| 1. Not practicable | Valid | The PM must explain why the method cannot be built as drawn. |
| 2. Missing information | Valid | The one you control — and the one the 25% retention turns on. Close it and it disappears. |
| 3. Not realistic | Valid | But the PM must say what is unrealistic. "Too optimistic" with no analysis is not a reason. |
| 4. Does not comply with the Scope | Valid | Ask which Scope clause the programme conflicts with. |
| Disagreeing with your method | NOT valid | If the sequence is practicable, realistic and compliant, preference is not a ground. |
| Fear of conceding a compensation event | NOT valid | Acceptance does not concede entitlement, and worrying that it might is not a ground. |
Gateway approvals are acceptances from Others, so clause 31.2 requires them on the programme. They are also enormous, and most programmes understate them badly.
48 weeks in London. No construction on a higher-risk building may start until it is approved, and over 1,500 applications have been sitting in progress.
A 12-week allowance understates it by 40 weeksThe approval rate has run at about 77%. The tool computes a probability-weighted duration including the resubmission branch, rather than assuming first-time success.
Expected duration, not best caseCompletion certificate before occupation. Cases have waited more than 500 days — that is revenue deferred, not just a milestone missed.
Occupation, and income, wait on itEleven items. One checklist. A quarter of your money.
The form isn't connected to anything yet, so nothing was sent and no order was placed.
To get in touch for real, email sales@projectcontrolcenter.co.uk.